Customize Tracking for your Measures


Article Summary

While we've provided you with a default 0-100 % range whenever a measure is tracked, you can customize it further to maintain your measures by keeping the values within, above or below the specified ranges. Choose Maintain between, Maintain above or Maintain below in the Target type dropdown in the Tracking section to enable this customization! You can also set critical limits which will help you with the health calculation (see What does each Health mean in Cascade?) and visualization of the progress chart.

Note that the health % gets “clamped” to be between 0 -100%. If a value is large or smaller than that, then it'll be rounded off to the closest value (i.e., if you had -20%, then it gets rounded to 0%).

In the case of maintaining a measure within a range, the critical limits (lower or upper ranges) that you set will serve as a tolerance limit, and correlate with your tracking mechanism, thereby controlling the health of your measure!

If you wish to pull insights from measures that've "maintain targets" specified, you can use "Single Measure Performance" widget or "Current State of Measure" widget in your dashboards or create a "Measures table" in your report and apply filter as "Condition is maintain or Not maintain"!

How does maintain measure work?

With maintain measures, you can:

  1. set up a target to "achieve" (can be a range)
  2. set critical limits to calculate health, and visualize the chart showing up the lower and upper limit numbers that you want to display. But this'll also serve as a tolerance limit for measures set to "maintain in between". Any progress made beyond the critical limits will straight away make the health to be At risk!

The above two options provide a higher level of granularity, and thereby determine the health calculation!

Depending on the targets you set, the maintain options you choose, and the due dates, your measure's health will be determined. Based on the progress that you make, the progress calculation will be
(Current value - Lower or Upper critical)/ (Lower or Upper limit - Lower or Upper critical)

If the progress updated meets the targets set in the maintain options, and the due date is still in the future, then it would show up as On track. Any value beyond the critical limits will straight away make the health to be At risk!

The health is based on the thresholds you set and it’s a sliding scale. As you get further from the target, it'll go from On track to Behind to At risk. The further that threshold is from the main target the slower the health will go down. The health statuses will display as On track (>=95% or when the progress meets the maintain targets), Behind (>=85% to 94%), and At risk (<84%), based on the actual progress and the upper-lower limits that you set.

Now, let's see how each option works!

Maintain In Between:

Use this tracking customization when you want your target to be between a range. For example, a good CSAT is any value between 90 and 100. So, when the progress is any of the numbers in this range, the measure is said to be on track till the due date! And, if you set critical limits as 75 and 100, then if your progress is between 75 to 90, or greater than 100, the health will vary to be on track, behind or at risk!

For "Maintain between", the progress and health calculation is (Current value - Lower or Upper critical)/(Lower or Upper limit - Lower or Upper Critical) based on the actual value!

Let's consider this example:

The units produced per day should be maintained between 4000 and 4500, with the Lower critical at 1000 and Upper critical at 5000.

  • If the progress made is any value between 4000 and 4500, then it would be within the range and the health will be On track!
  • If the progress is say, 3800, then this'll use the "lower values" for calculation which is (3800-1000)/(4000-1000) = 93%. The health will be displayed as Behind (>= 85% to 94%).
  • If the progress is say, 4800, then this'll use "upper values" for calculation which is (4800-5000)/(4500-5000) = 40%. The health will be displayed as At risk (< 84%).
  • Past the due date, if the progress is within the 4000 and 4500, then the health would be Achieved, and with any other value outside the limit, the health will vary based on the calculations.

This is how the preview of the goal hub will look like:

Maintain Above:

Use this tracking customization when you want your target to be above a certain value. For example, maintaining platform uptime availability above 75%. You can also use this customization when you want to maintain both the initial and target value at the same level, i.e., you want 100% of your employees to enable SSO, and it should always be 100%, then you can choose this option and say maintain above 100%, in which case, this'll be on track till the due date!

For "Maintain above", the progress and health calculation is (Current value - Lower critical)/(Lower limit - Lower Critical)

Let's consider this example: 

The First pass yield must always be maintained above 85%. So in this case, the Lower limit is 85% and the Lower critical is 50 and the Maximum value is 100.

  • If the progress made is, say 82, then the calculation will be (82-50)/(85-50) = 91%. The health will be Behind (>= 85% to 94%)!
  • Straight off, for any value above 85, the health will be On track! And, for any value below the lower critical of 50, the health will be At risk!
  • Past the due date, if the progress is above 85, then the health would be Achieved, and with any other value outside the limit, the health will vary based on the calculations.

This is how the preview of the goal hub will look like! The dots represent the actual progress made on those days.

Maintain Below:

Use this tracking customization when you want your target to be below a certain value. For example, average response time is good if its below 3 hours. So, when the progress is any number below 3 hours, the measure is set to be on track, till the due date!

For "Maintain below", the progress and health calculation is (Current value - Upper critical)/(Upper limit - Upper Critical)

Let's consider this example: 

The Takt time must be maintained below 30 seconds. In this case, the Upper limit is set at 30 and the Minimum value is 0 and the Upper critical is 50.

  • If the progress made is, say 35, then the calculation will be (35-50)/(30-50) = 75%. The health will be At risk (< 85%)!
  • Straight off, for any value below 30, the health will be On track! And, for any value above the upper critical of 50, the health will be At risk!
  • Past the due date, if the progress is below 30, then the health would be Achieved, and with any other value outside the limit, the health will vary based on the calculations.

This is how the preview of the goal hub will look like! The dots represent the actual progress made on those days.

FAQs

I want to make a progress for a date in the past!

There is no option to make historical data points with maintain measures.

What happens if the measure is past the due date?

If the progress is within the range that's set, then the health of On track will be changed to Achieved. However, if the progress is outside the range or limits, then based on the progress calculations, the health labels are showed! 

Can I pull insights on these maintain measures?

Yes! If you wish to pull insights from measures that've "maintain targets" specified, you can use "Single Measure Performance" widget or "Current State of Measure" widget (single measure performances) in your dashboards or create a "Measures table" in your report and apply filter as "Condition is maintain or Not maintain"!

I do not see the Edit data table to change the expected progress!

Yes, that's the intended behavior! With maintain measures, the due date and the critical limits that you set impact the progress and thereby the health of the measure. There is no concept of expected progress with maintain measures and that's why you'll not be able to see the table to make any changes.


Was this article helpful?